Employer: Azerbaijan Amelioration and Water Management Open Joint Stock Company
Main Contractor: SADE CGTH
Subcontractor: RAMCO CJSC
Brief description of the performed works: Construction works of water supply & sewerage networks, preparing the layout of water supply & sewage facilities and plans of the sewage network, pump stations, reservoirs. Design, build, installation operation and maintenance of wastewater collectors and wastewater treatment plant.
Dimension of performed works: 193 722m – potable water line; 170 996m – waste water line; WWTP capacity – 10 000 m³/d
Date of contract award: 27.12.2010
Date of contract completion: 31.05.2019